schedule:
 filming schedule
13th to the 14th film scene 1
15th to the 16th film scene 2
17th to the 20th film scene 3
21st to the 22nd film scene 4
23rd to the 24th film scene 5
27th to the 28th film scene 6
29th to the 30th film scene 7

sound schedule:
31st to the 3rd to get all sounds completed for the sequence.

visual/special effects:
4th to the 7th is the effects time.

final edit/all done:
10th to the 14th finish the sequence.

casting:

Xavier = sam.
asher = will.

head teacher = chris.
mindy = girl in group.
milo = charlie.


Locations:
already done.